London Kitchen Extension Guide — GPDO Class A, 6m Wraparound Economics, Part F Ventilation, £2,500-£4,200/m²
London kitchen extension reality. 6m wraparound vs 4m rear economics, GPDO Class A vs full planning, 5-7m steel spans, Gas Safe isolation, Part F ventilation, Building Control. £75K-£180K all-in. One verified contractor.
The "design then permit then build" sequence costs 14-18 weeks of front-loaded time and never costs more than the project was already going to cost. The "build then apply for retrospective planning" sequence costs 6-12 months of dispute, £15,000-£40,000 in rectification, and occasionally an enforcement notice requiring the extension to be demolished. Here is what sits inside each route, and why Building Control sign-off is not optional.
Kitchen extensions are the highest-volume structural project in London — roughly 40,000 are completed annually across the 32 London boroughs, and approximately one in eight of those starts without one or more of the required consents. The shortfalls are never accidental. They are the product of homeowners being told, by cowboys quoting 30 per cent under market, that "we don't need planning" or "Building Control is a waste of money" or "your neighbour won't mind". Twelve months later, a retrospective Lawful Development Certificate application fails, the borough's Planning Enforcement team issues a notice, the neighbour serves a county court party-wall claim, and the extension either comes down at the owner's cost or survives via an expensive planning appeal with Enforcement Officer testimony on the record.
This guide walks the legitimate route for a London kitchen extension in 2026 — under the Building Regulations 2010, the Town and Country Planning (General Permitted Development) (England) Order 2015, the Party Wall etc. Act 1996, the Gas Safety (Installation and Use) Regulations 1998, and the various Approved Documents (A, B, C, F, L, P) that govern what competent construction actually looks like.
6m wraparound vs 4m rear-only — the economics that drive the design
Most London kitchen-extension briefs arrive from the client as "I want a bigger kitchen with bifold doors onto the garden". What the architect is actually being asked is: given the floor plan of a typical London terrace, what extension footprint creates the most usable room per pound spent? The answer in London — contrary to instinct — is almost always the wraparound, not the rear-only.
A rear-only single-storey extension under GPDO Class A permits up to 3 metres depth for an attached house (terrace or semi-detached) or 4 metres for a detached house — see Schedule 2, Part 1, Class A of the GPDO 2015 for the full qualifying criteria. Under the Larger Home Extension route via Prior Approval and the Neighbour Consultation Scheme, those limits double to 6 metres attached and 8 metres detached. A typical London terrace is 4.5-5.5 metres wide. A 4-metre rear extension on a 5-metre-wide terrace adds about 20m² of gross floor area. A 6-metre rear extension adds about 30m².
A wraparound combines a rear extension with a side-return infill — the side return being the narrow strip of garden (typically 1.2-1.8 metres wide) alongside the original kitchen. Wrapping the side return into the footprint does not materially increase depth but dramatically improves the plan geometry: the existing kitchen merges with the new rear extension and the side-return infill into one open-plan room, typically 28-40m² combined, with usable circulation, an island, and a sensible relationship between the cooker and the garden doors.
The per-m² build cost of a wraparound is higher than a rear-only extension (£3,200-£4,200/m² vs £2,500-£3,400/m² for a single-storey rear of equivalent spec) — because the ratio of expensive perimeter detailing (steel, foundations, glazing lines) to cheap floor area gets worse as you add the side return. But total project cost on a larger useable room is more defensible per m² than a smaller, less functional room — and the resale uplift in most London postcodes favours wraparounds over rear-only extensions by approximately £40,000-£90,000 on a standard 3-bed terrace.
Rear-only economics at typical 2026 London pricing:
- 20m² rear at mid-spec — £55,000-£68,000 shell, £75,000-£90,000 all-in.
- 30m² rear (Larger Home Extension at 6m depth) at mid-spec — £80,000-£100,000 shell, £110,000-£135,000 all-in.
Wraparound economics at the same pricing tier:
- 28m² wraparound at mid-spec — £90,000-£118,000 shell, £120,000-£145,000 all-in.
- 35-40m² wraparound at mid-spec — £115,000-£150,000 shell, £145,000-£180,000 all-in.
All-in figures above include Party Wall surveyor fees, structural engineer, architect (RIBA Stages 1-4), Building Control, and reasonable contingency (7.5-10 per cent) but exclude kitchen furniture and appliance installation (typically a further £18,000-£50,000 for mid-to-premium spec).
Planning vs permitted development — GPDO Class A interactions with Article 4
A kitchen extension in London is not automatically permitted development. Class A of GPDO Schedule 2 Part 1 permits certain single-storey rear extensions without planning, subject to numerous tests — and those tests are cumulative, meaning previous extensions on the property count against your allowance and buying the house does not reset it.
Class A is removed entirely where any of the following apply:
- The property is a flat or maisonette (Class A applies only to houses).
- The property is listed under the Planning (Listed Buildings and Conservation Areas) Act 1990 — Listed Building Consent is separately required, and Class A is disapplied.
- The property is in a Conservation Area with tightened restrictions (side extensions lose Class A rights in Conservation Areas).
- An Article 4 Direction under Article 4 of the GPDO removes Class A rights for the defined geographic area.
- The extension exceeds the dimensional limits (3m/4m depth, 4m height, height within 2m of boundary capped at 3m).
Inner London Article 4 coverage relevant to kitchen extensions:
- Hackney — De Beauvoir, Stoke Newington, Clapton, Dalston, London Fields conservation areas all under Article 4.
- Camden — most of the borough's conservation areas under Article 4.
- Islington — conservation areas mostly under Article 4 (Canonbury, Barnsbury, Highbury Fields, De Beauvoir west).
- Kensington & Chelsea — widespread Article 4 coverage in conservation areas.
- Haringey — borough-wide Article 4 covering Tottenham ward areas (adopted 2019).
- Tower Hamlets — Spitalfields, Bow, Whitechapel conservation areas under Article 4.
- Southwark — Bermondsey, Dulwich Village, Herne Hill under Article 4.
- Lambeth — Brixton, Clapham Old Town, Stockwell conservation areas.
- Wandsworth — Battersea Park, Clapham Old Town, Balham under Article 4.
- Westminster — most of the borough is in conservation areas with tightened Class A.
The consequence in practice: approximately 30-45 per cent of inner-London terraces requiring a kitchen extension cannot rely on Class A permitted development and need full planning permission. The first check on any project — before design, before survey, before the deposit — is the borough's Local Plan constraints layer run at the exact address. Every borough publishes this as a free interactive map. Every homeowner who ignores it regrets the decision.
For Class A-eligible kitchen extensions, the safe route is a Lawful Development Certificate (LDC). The LDC is a £120 certificate from the borough confirming that the proposed works fall within GPDO Class A. It is not planning permission — it is a legal certificate that the works do not need planning permission. The LDC is evidence in a conveyancing pack five years later when the buyer's solicitor queries whether the extension had proper consent. Without an LDC, the buyer's solicitor commonly demands indemnity insurance (£250-£600 one-off) or an expedited retrospective application, which slows completion by 8-12 weeks.
For non-Class A kitchen extensions — Article 4 areas, Conservation Areas, listed properties, or oversized footprints — the route is full planning. Statutory target 8 weeks, realistic London average 10-13 weeks, consultation 21 days, officer or committee decision depending on objection count. Community Infrastructure Levy (CIL) applies where the extension creates more than 100m² of additional floor space — most kitchen extensions stay below the threshold, but very large wraparounds with lofts and rear two-storey elements can trigger CIL.
Structural steel at 5-7 metre spans — the calculations Building Control will want to see
The defining engineering question of a kitchen extension is the steel beam spanning the removed rear wall between the original kitchen and the new extension. On a terrace typically 5-5.5m wide with a load-bearing rear wall carrying first-floor joists and roof load, removing the wall to merge old kitchen and new extension into one open room requires a single rolled steel section spanning the full width.
For a 5-metre span carrying typical London terrace loads (first-floor joists at 400mm centres, pitched roof with slate covering, residential live load under BS EN 1991-1-1 of 1.5 kN/m²), the typical beam specification is a 203 × 133 × 30 UB or a 254 × 146 × 31 UB — sized by a qualified structural engineer to satisfy:
- Bending moment capacity at mid-span per BS EN 1993-1-1 Eurocode 3
- Shear capacity at supports
- Deflection limit typically span/360 for serviceability per BS EN 1990 Annex A1
- Lateral-torsional buckling check if compression flange is unrestrained
- Bearing at padstones sized per Eurocode 3 with concrete padstones typically 215 × 215 × 215mm minimum
- Fire resistance of 30 or 60 minutes per Approved Document B, achieved via intumescent paint to a specified dry film thickness, or boxed plasterboard to an approved specification
On a wraparound where the side return is being opened into the main space as well as the rear, you typically have two intersecting beams forming an L or a T. The junction requires a moment connection or a masonry return pier — specified by the engineer with bolt patterns, plate thicknesses, and weld details. On larger spans (6-7 metres for 6m Larger Home Extensions or wraparounds with very wide side returns) the engineer may specify a plate girder or a heavier UB (305 × 165 × 40 or 356 × 171 × 45) with larger padstones.
The output you need from the structural engineer before Building Control will sign off:
- Stamped structural calculations (bending, shear, deflection, LTB, padstone, connection)
- Structural drawings showing beam size, positions, padstones, bearing details, and connection details
- Professional Indemnity Insurance certificate (£1 million minimum; £2 million preferred for spans above 6m)
- Site inspection report signed after beam installation confirming compliance with approved drawings
Structural engineering fees for a simple rear extension with a single beam: £1,200-£2,500. For a wraparound with intersecting beams: £2,800-£5,500. Fabrication of steel: £1,200-£2,500 per beam delivered. Installation labour, padstones, propping, and Building Control inspection coordination: £2,500-£4,500 on a simple extension; £5,500-£9,000 on a complex wraparound.
Never accept a contractor's quotation that lumps "steels" into a single line item. The engineer, fabricator, and installer are three separate roles, and the homeowner needs to see all three costs itemised.
Building Control — LABC vs Approved Inspector
Every kitchen extension requires Building Control approval regardless of whether planning is required. Two legitimate routes:
Local Authority Building Control (LABC) — the borough's statutory inspection service. Fees £600-£1,100 for a typical extension. Two submission routes:
- Full Plans — drawings and calculations submitted for approval before work starts. Approval takes 3-5 weeks. Lowest risk: any non-compliance is caught on paper, not on site.
- Building Notice — inspections stage-by-stage on site as work progresses, no prior plan approval. Higher risk: non-compliance discovered on site must be rebuilt. Building Notice is appropriate for simple works; avoid for anything involving steel or excavation near neighbours.
Approved Inspectors — private-sector competitors offering statutory approval under the Building Act 1984. Faster plan review (5-10 working days typical vs 3-4 weeks for LABC). Fees £800-£1,600. Under the Building Safety Act 2022, all legitimate Approved Inspectors are listed on the Building Safety Regulator's register. Reject any Building Inspector who is not on the register — unregulated inspection is worthless at conveyancing.
Mandatory inspections (either route): foundation excavation before concrete pour; damp-proof course before slab; oversite concrete and drainage; superstructure shell including steel beam bearings; pre-plaster with insulation, vapour control layer, and fire-stopping visible; and final completion. The Completion Certificate is issued on final sign-off and is required evidence at any future conveyancing — without it, mortgage lenders flag the property and buyers' solicitors demand retrospective Regularisation Certificates opening up finished work.
Gas Safe — isolation, relocation, and the certificate at the end
The kitchen extension almost always involves gas work — relocating the hob, extending the gas run to a new position, or installing a new boiler location. This is regulated by the Gas Safety (Installation and Use) Regulations 1998 and is a criminal offence if carried out by an unregistered person.
Only Gas Safe Registered engineers may work on gas installations in England, Scotland, and Wales. Gas Safe replaced the old CORGI scheme in 2009 and is the sole legal register operated under contract to the Health and Safety Executive. Before any gas work, verify the engineer's Gas Safe ID card — every card has a photograph, an engineer number, and a list of work categories the engineer is competent for (cookers, boilers, meters, fires, and so on — categories are separate, and a gas engineer registered for cookers is not automatically qualified for boilers). Check the ID card against the Gas Safe Register online — the register is free to search and always current.
The gas-work sequence during a kitchen extension:
- Isolation — gas supply is isolated at the meter by a Gas Safe engineer before any demolition that affects gas pipe routing. Never start demolition with live gas pipes in the wall.
- Capping — pipes are capped at accessible points and isolated with a certificate issued.
- Relocation — new gas runs installed in copper (typically 22mm for a hob, 28mm for a boiler) with tightness test at completion.
- Certification — a Gas Safety Certificate (landlord's certificate format or homeowner CP12-equivalent) issued on commissioning. Keep this with the property deeds.
The cost of a gas relocation for a hob within 3 metres of the original position: £250-£450 including materials. For a boiler relocation: £800-£1,800. For a new combi boiler installation compliant with ErP directive efficiency and Boiler Plus 2018 controls: £2,400-£4,200 fully fitted including flue, controls, and condensate drain.
Part F 2023 ventilation — the requirements new kitchens must meet
Approved Document F (Volume 1: Dwellings) covers ventilation. Part F 2023 sets the minimum ventilation requirements for kitchens in new work:
- Kitchen extract fan — minimum intermittent rate of 60 litres per second for a cooker hood discharging to atmosphere, or 30 l/s for a general kitchen extract fan if no cooker hood is fitted.
- Continuous background ventilation — trickle vents in windows rated at 8000 mm² equivalent area per wet room, and 5000 mm² equivalent area for a kitchen.
- Make-up air provision where extract rate exceeds 40 l/s — typically achieved via trickle vents or a mechanical ventilation system.
- Duct routing — cooker hood extract must discharge to atmosphere via ducting of minimum internal diameter 150mm for most domestic hoods, with duct length and bend-count limited to maintain fan performance curve. Recirculating hoods that return filtered air to the kitchen do not satisfy Part F on a newbuild/extension and will fail Building Control unless supplementary extract is provided.
- Sound limits — intermittent extract fans capped at 30 dB(A) in habitable rooms.
- MVHR option — Mechanical Ventilation with Heat Recovery is increasingly specified on high-spec extensions, providing continuous low-rate background extract with heat recovery. MVHR adds £3,500-£6,500 to the project and requires its own commissioning certificate. On highly airtight extensions (air permeability below 5 m³/h·m² at 50Pa), MVHR is effectively mandatory to avoid condensation and air quality issues.
Cooker hood ducting is a common Building Control failure point. Recirculating hoods are sold aggressively to homeowners on the basis of easier install — but they do not satisfy Part F on a new kitchen and the lack of extract at the end of a 12-month project means the Completion Certificate is withheld until ducted extract is installed.
Part L 2023 — fabric standards for new kitchen extensions
Approved Document L 2023 sets U-value limits for new elements. A kitchen extension is new construction and must meet the new-build limits, not the retrofit limits:
- Walls — 0.18 W/m²K (typically met with 100mm PIR in full-fill cavity plus 40mm PIR internal lining, or 170mm full-fill mineral wool in a wider cavity)
- Pitched roof — 0.16 W/m²K
- Flat roof — 0.18 W/m²K (warm-deck construction with 150mm PIR over deck is standard)
- Windows, rooflights, bifold doors — 1.4 W/m²K for the whole unit
- Floor — 0.18 W/m²K (100mm PIR under solid slab, typical spec)
Air permeability target on new dwellings is 8 m³/h·m² at 50Pa under Part L 2023. Extensions are tested as part of the overall dwelling envelope where practical. Thermal bridging is separately assessed via Accredited Construction Details or project-specific Psi-value calculations through a SAP assessment.
The 2023 standards are tighter than the 2013 standards that a lot of London builders still specify from memory. A cavity wall drawn to 2013 U-value targets will fail a 2023 plan check — specifically, the cavity fill and internal lining combination have to increase. If the architect's drawings reference "compliance with Part L" without a specific date, challenge them — "compliance with Approved Document Part L 2023" is what Building Control will check against, and retrofitting insulation to meet Part L 2023 after shell completion is painful.
Build programme — 16 to 24 weeks permission to handover
A typical single-storey kitchen extension in London, measured from the date planning/Prior Approval/LDC is issued:
- Weeks 1-4 — Party Wall notices complete, contract signed, structural engineer calcs finalised, steel order placed, kitchen ordered on a 6-10 week lead time, site set-up, welfare facilities installed.
- Weeks 4-8 — Demolition of rear wall and scaffolding, foundation excavation with Building Control inspection, concrete pour, damp-proof course, oversite slab.
- Weeks 8-12 — Masonry shell to DPC, steel beam installation with Acrow propping, Building Control bearing sign-off, shell to roof plate.
- Weeks 12-15 — Roof structure, warm-deck build-up, rooflights installed, windows and bifold doors installed, weather-tight shell achieved.
- Weeks 15-18 — First-fix M&E including gas relocation (Gas Safe engineer isolates and reroutes), plumbing, electrical, insulation, vapour control layer, plasterboard, pre-plaster inspection.
- Weeks 18-22 — Plastering (typically 2-week drying period before decoration), second-fix M&E, kitchen installation (pre-ordered units arrive at Week 19-20), appliances, tiling.
- Weeks 22-24 — Decoration, flooring, gas commissioning with certificate, MVHR commissioning if fitted, snagging, Building Control final inspection, Completion Certificate.
A wraparound extension runs 20-28 weeks. Winter programming (October-February) adds 2-3 weeks to the shell phase due to rain, short daylight, and concrete-curing delays — schedule foundation and shell works March-September where feasible.
The "design then permit then build" vs the "build then apply" sequence
The correct sequence is:
- Survey and feasibility (weeks 1-3)
- Architect design to RIBA Stage 3 (weeks 3-8)
- Planning application or Prior Approval or LDC (weeks 8-21)
- Structural engineer calculations finalised (weeks 18-22, overlapping)
- Building Control Full Plans submission (weeks 20-24, overlapping)
- Tender to 3-5 contractors (weeks 22-26)
- Contract award (week 26-28)
- Party Wall notices served (weeks 24-28, subject to 1-2 month notice periods before start on site)
- Start on site (weeks 28-30)
- Handover (weeks 44-54)
The cowboy sequence is:
- Homeowner gets a quote from a contractor met at B&Q (week 1)
- Deposit paid (week 2)
- Start on site (week 3)
- Neighbour complains to borough Planning Enforcement (week 6)
- Planning Enforcement Officer visits, issues a temporary stop notice (week 7-8)
- Retrospective planning application refused (weeks 14-22)
- Works ordered removed or materially altered (weeks 22-50)
Retrospective planning is technically possible but legally weaker than pre-commencement planning — the Enforcement Officer's report is on file, the council has a motivated neighbour, and the planning committee sees a property owner who proceeded in bad faith. Retrospective applications in inner London conservation areas succeed at roughly 20 per cent; refused cases face enforcement notices, and appeals take 6-14 months through the Planning Inspectorate with no certainty of success.
What Baily verifies before any London kitchen extension match
Every London contractor Baily introduces for a kitchen extension has passed an eight-point verification specific to this project type:
- Current NHBC or LABC Warranty registration — 10-year structural warranty on completion.
- Structural Engineer panel or named partner with £1 million Professional Indemnity Insurance minimum, current run-off cover, stamped calculations for every beam specified.
- Gas Safe registered gas engineer in-house or named sub-contractor, with verified ID against the Gas Safe Register.
- NICEIC or NAPIT registered electrician for Part P compliance.
- TrustMark government-endorsed quality scheme registration with active complaints handling.
- CHAS, SafeContractor, or Constructionline accreditation for CDM 2015 health and safety competence.
- Party Wall Surveyor panel registered with RICS or FPWS, and three closed Party Wall Awards on file in your borough within the last 18 months.
- Public liability £5 million minimum and employer's liability £10 million per the Employers' Liability (Compulsory Insurance) Act 1969. Fair payment terms — deposit capped at 10 per cent, stage payments tied to verifiable milestones, minimum 2.5 per cent retention held 12 months against defects.
Checkatrade gives you five names and charges them for the privilege of your lead. AskBaily matches you with one London contractor who has already passed Gas Safe, NHBC, and Building Control checks, whose structural engineer knows your borough's LABC inspectors by name, and whose last completed wraparound in your postcode is walkable before you sign a contract.
Frequently asked questions
Can I build a 6-metre rear kitchen extension under permitted development in London?
Only via the Larger Home Extension Prior Approval route under GPDO Class A, and only if your property is not in an Article 4 zone, not in a Conservation Area with Class A restrictions, not listed, and not a flat. In practice approximately 30-45 per cent of inner-London terraces cannot use Larger Home Extension because Article 4 Directions have removed the right. Check your borough's constraints layer before design. If Larger Home Extension applies, submit the Prior Approval application with drawings and a £120 fee — neighbours have 21 days to object, and the determination window runs 42 days from receipt. If no objections or if the officer approves over objections, you can proceed. If refused, your only route is full planning (8-13 weeks on top of the 42 days already spent).
What happens if I install recirculating cooker hood instead of ducted extract?
Your Building Control Completion Certificate is withheld. Approved Document Part F 2023 requires a minimum intermittent extract rate of 60 l/s for a cooker hood on a new-build/extension, discharging to atmosphere via ducting of minimum 150mm internal diameter. A recirculating hood returns filtered air to the kitchen and does not satisfy Part F. Installers sometimes sell recirculating hoods on the basis of easier installation (no external ducting required), and homeowners find out at the end of a 10-month project that Building Control will not issue the Completion Certificate until ducted extract is installed. If external ducting routing is genuinely impossible in your property configuration, an MVHR system providing continuous mechanical extract can satisfy Part F as an alternative route — but it must be specified from day one, not retrofitted after the kitchen is installed.
How much does the structural steel actually cost for a 5-metre open span?
For a 5-metre clear span on a typical London terrace carrying standard first-floor joist and pitched-roof loads: structural engineer's stamped calculations and drawings £1,200-£2,500; steel fabrication (typically a 203 × 133 or 254 × 146 UB) delivered £1,200-£2,500 per beam; installation including temporary Acrow propping, padstone installation, and Building Control inspection £2,000-£3,500; intumescent paint fire protection £400-£900. Total steelwork on a single-opening rear extension: £4,800-£9,400. On a wraparound with intersecting beams and a moment connection or plate girder: £10,500-£18,000. Never accept a quote that bundles "steelwork" into a single line — you need engineer, fabricator, and installer priced separately, and you need the engineer's PI insurance certificate before deposit.
Do I need planning permission in Hackney, Camden, or Islington for a rear kitchen extension?
Almost always yes — inner London boroughs operate widespread Article 4 Directions and Conservation Area designations that strip or tighten Class A permitted development rights. In Hackney, Article 4 covers most of De Beauvoir, Stoke Newington, Clapton, Dalston, and London Fields. In Camden, most conservation areas (and most of the borough is covered) have Article 4 plus Conservation Area restrictions. In Islington, the conservation area coverage is extensive and Class A is removed across most of Canonbury, Barnsbury, Highbury Fields, and De Beauvoir west. Run the borough's constraints map at your exact address — every borough publishes a free interactive layer showing Article 4, Conservation Areas, listed buildings, TPOs, and flood zones. The map is authoritative; every pub-chat claim about "my mate in your street didn't need planning" is wrong.
What is the real total cost of a London kitchen extension including everything?
For a standard mid-spec 25-28m² single-storey rear extension to Class A or Larger Home Extension: £85,000-£130,000 all-in including structural engineer, Party Wall surveyor, architect fees RIBA Stages 1-4, Building Control, steel, shell construction, weathertight envelope, internal fit-out to plaster, kitchen furniture and appliances (£18,000-£35,000), flooring (£4,000-£8,000), and reasonable contingency at 7.5-10 per cent. For a mid-spec 32-40m² wraparound: £130,000-£180,000 all-in. For high-spec specifications with premium glazing, bespoke kitchen, underfloor heating, MVHR, and air-source heat pump: add 25-40 per cent. For listed or heritage-grade specifications: add 40-70 per cent. Reject any quotation at £1,200-£1,800/m² — the cost base of London construction in 2026 does not support those rates, and the contractor is either underpricing to win the job then raising variations, or cutting corners on steel, insulation, or Gas Safe sign-off that will surface as a problem 6-18 months later.
Citations and references
Where in London we match contractors
Each neighborhood has distinct Article 4 Direction + conservation posture. Baily pre-scopes against the specific overlay your home sits under.
- ShoreditchLondon Borough of Hackney
- ChelseaRoyal Borough of Kensington and Chelsea
- Notting HillRoyal Borough of Kensington and Chelsea
- IslingtonLondon Borough of Islington
- CamdenLondon Borough of Camden
- HackneyLondon Borough of Hackney
- WestminsterWestminster City Council
- KensingtonRoyal Borough of Kensington and Chelsea
- MaryleboneWestminster City Council
- MayfairWestminster City Council
- ClaphamLondon Borough of Lambeth
- FulhamLondon Borough of Hammersmith and Fulham
- HampsteadLondon Borough of Camden
- HighgateLondon Borough of Camden / Haringey
- GreenwichRoyal Borough of Greenwich
- RichmondLondon Borough of Richmond upon Thames
- WimbledonLondon Borough of Merton
- BatterseaLondon Borough of Wandsworth
- BrixtonLondon Borough of Lambeth
- PeckhamLondon Borough of Southwark
Ask Baily about your London project
One vetted contractor, not twelve strangers.
Loading chat…
Who is Baily?
Baily is named after Francis Baily — an English stockbroker who retired at 51, became an astronomer, and in 1836 described something on the edge of a solar eclipse that nobody had properly articulated before: a string of bright beads of sunlight breaking through the valleys along the moon’s rim.
He wasn’t the first to see them. Edmond Halley saw them in 1715 and barely noticed. Baily’s contribution was clarity — describing exactly what was happening, in plain language, so vividly that the whole field of astronomy paid attention. The phenomenon is still called Baily’s beads.
That’s what we wanted our AI to do. Every inbound call and text has signal in it — a homeowner’s real question, a timeline, a budget, a hesitation that means “yes but.” Baily listens to every one, 24/7, and finds the beads of light.
Baily was a businessman before he was a scientist. That’s our vibe too.